WENK Pneumatic 3A/4A Air Control Valve
Product Detail
Acting Mode |
External Control |
Working Media |
Air |
Working Pressure |
0~1.0Mpa |
Proof Pressure |
1.5Mpa |
Working Temperature Range |
-5℃~60℃ |
Body Material |
Aluminum Alloy |
3A/4A Series Pneumatic Control Valve User Manual

1. Product Overview
The WENK Pneumatic 3A/4A Series Pneumatic Control Valve is a high-performance directional control valve designed for precision control in pneumatic systems. Featuring a compact aluminum alloy body with mirror finish and hard oxidation treatment, this valve offers exceptional durability and long service life.
The 3A series is 3-port 2-position type, while the 4A series is 5-port 2/3-position type, providing versatile solutions for various automation applications.

2. Technical Specifications
2.1 Basic Parameters
- Series: 3A/4A
- Type: Pneumatic Control Directional Valve
- Working Medium: Compressed air filtered through 40μm filter
- Action Mode: Internal pilot type
- Lubrication: Not required
- Working Pressure Range: 0~1.0 MPa
- Maximum Proof Pressure: 1.5 MPa
- Operating Temperature Range: -5~60°C
- Maximum Action Frequency: 5 cycles/second
- Minimum Excitation Time: 0.05 seconds
2.2 Structural Parameters
- Valve Body Material: Aluminum alloy
- Seal Material: NBR
- Connection Type: Pipe connection
- Port Size:
- 3A Series: G1/8"
- 4A Series: G1/8", G1/4", G3/8", G1/2" (depending on model)
- Effective Cross-sectional Area:
- 3A Series: 14 mm² (Cv=0.78), 16 mm² (Cv=0.89)
- 4A Series: 12 mm² (Cv=0.67), 14 mm² (Cv=0.78), 16 mm² (Cv=0.89), 30 mm² (Cv=1.68), 50 mm² (Cv=2.79) (depending on model)
- 3A Series: G1/8"
- 4A Series: G1/8", G1/4", G3/8", G1/2" (depending on model)
- 3A Series: 14 mm² (Cv=0.78), 16 mm² (Cv=0.89)
- 4A Series: 12 mm² (Cv=0.67), 14 mm² (Cv=0.78), 16 mm² (Cv=0.89), 30 mm² (Cv=1.68), 50 mm² (Cv=2.79) (depending on model)

3. Installation Steps
-
Pre-installation Preparation
- Confirm that the air supply pressure is within the range of 0.15~0.8 MPa
- Ensure the air supply has been filtered through a 40μm filter
- Check that the valve model matches the installation requirements
-
Installation Location Selection
- Choose a well-ventilated location away from direct sunlight
- Ensure there is sufficient space around the valve for operation and maintenance
- Avoid installing on equipment with severe vibration
-
Piping Connection
- Confirm that the pipes are clean and free of impurities and moisture
- Connect the air inlet (P), air outlet (A/B), and exhaust port (R/S) according to the markings on the valve body
- Use appropriate sealing material (such as PTFE tape) to ensure a tight connection
- Be careful not to over-tighten the pipes to avoid damaging the valve body
-
Fixed Installation
- Use suitable bolts to fix the valve to the mounting surface
- Ensure the valve is securely installed without looseness
Pre-installation Preparation
- Confirm that the air supply pressure is within the range of 0.15~0.8 MPa
- Ensure the air supply has been filtered through a 40μm filter
- Check that the valve model matches the installation requirements
Installation Location Selection
- Choose a well-ventilated location away from direct sunlight
- Ensure there is sufficient space around the valve for operation and maintenance
- Avoid installing on equipment with severe vibration
Piping Connection
- Confirm that the pipes are clean and free of impurities and moisture
- Connect the air inlet (P), air outlet (A/B), and exhaust port (R/S) according to the markings on the valve body
- Use appropriate sealing material (such as PTFE tape) to ensure a tight connection
- Be careful not to over-tighten the pipes to avoid damaging the valve body
Fixed Installation
- Use suitable bolts to fix the valve to the mounting surface
- Ensure the valve is securely installed without looseness

4. Operation Guide
-
Initial Start-up
- Slowly open the air supply and observe if the valve operates normally
- Check for leaks at all connections
- Confirm that the valve action direction meets requirements
-
Normal Operation
- Control the valve switching through control signals
- Regularly check if the valve operates smoothly and accurately
- Monitor the pressure gauge to ensure working pressure is within the specified range
-
Emergency Stop
- In case of emergency, close the air supply shut-off valve
- If abnormal sounds or leaks are detected, stop use immediately and inspect
Initial Start-up
- Slowly open the air supply and observe if the valve operates normally
- Check for leaks at all connections
- Confirm that the valve action direction meets requirements
Normal Operation
- Control the valve switching through control signals
- Regularly check if the valve operates smoothly and accurately
- Monitor the pressure gauge to ensure working pressure is within the specified range
Emergency Stop
- In case of emergency, close the air supply shut-off valve
- If abnormal sounds or leaks are detected, stop use immediately and inspect

5. Maintenance
-
Daily Inspection
- Check for leaks at all connections
- Observe if the valve operates smoothly without abnormal noise
- Check if the air supply pressure is within the specified range
-
Regular Maintenance
- Every 3 months:
- Clean the exterior of the valve to remove dust and dirt
- Check if the pipe connections are secure
- Every 6 months:
- Inspect the condition of seals and replace them if aging or damage is found
- Clean the interior of the valve body to remove possible impurities
- Annually:
- Perform comprehensive performance testing
- Replace aging components such as springs and seals
-
Long-term Storage
- If not used for a long period, clean the interior and exterior of the valve
- Apply anti-rust agent to protect metal components
- Store in a dry, well-ventilated environment
- Regularly check the storage condition to prevent moisture and corrosion
Daily Inspection
- Check for leaks at all connections
- Observe if the valve operates smoothly without abnormal noise
- Check if the air supply pressure is within the specified range
Regular Maintenance
- Every 3 months:
- Clean the exterior of the valve to remove dust and dirt
- Check if the pipe connections are secure
- Every 6 months:
- Inspect the condition of seals and replace them if aging or damage is found
- Clean the interior of the valve body to remove possible impurities
- Annually:
- Perform comprehensive performance testing
- Replace aging components such as springs and seals
Long-term Storage
- If not used for a long period, clean the interior and exterior of the valve
- Apply anti-rust agent to protect metal components
- Store in a dry, well-ventilated environment
- Regularly check the storage condition to prevent moisture and corrosion

6. Precautions
- Do not use the valve exceeding the maximum proof pressure
- Avoid installing the valve in corrosive environments unless special protective measures are taken
- Do not use the valve with media other than compressed air unless specifically stated
- Before performing maintenance, always shut off the air supply and release system pressure
- Regularly check the working status of the valve to detect and resolve issues promptly
- If any abnormal conditions are found, stop use immediately and inspect
- When replacing parts, use genuine WENK Pneumatic accessories to ensure product performance and safety